What percentage of completion do factory-built construction sections usually have when leaving the factory?

Prepare for the RECA Residential Exam with targeted flashcards and multiple choice questions. Each question includes hints and explanations. Ensure your success with our engaging practice materials!

Factory-built construction sections typically leave the factory at a completion percentage of around 95%. This high level of completeness is due to the controlled factory environment where construction can be carried out efficiently. In a factory setting, builders can utilize consistent techniques, materials, and equipment, allowing for a significant part of the construction to be finalized before the sections are delivered to the building site.

As a result, by the time these sections are ready to leave the factory, they often include essential features such as plumbing, wiring, and insulation. This high completion percentage facilitates a quicker assembly on-site since most of the work has already been done, reducing labor costs and construction time significantly. Additionally, completing most components in a factory reduces the risks associated with weather and other on-site variables, enhancing the overall quality of the construction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy